Question: 2 For which task would you want to turn off effort-driven scheduling? O If one person is assigned to test code for 40 hours over
2 For which task would you want to turn off effort-driven scheduling? O If one person is assigned to test code for 40 hours over 5 days, you might assign a second person to test code so the testing is completed in half the time. The tal work still 40 hours, but the work is divided between two people. This task is effort-driven. obtaining requirements O a delivery milestone 5 pts O a delivery milestone