Question: 2. Given that the expected duration for a project path was 36 days and further suppose that someone calculated the standard deviation for the project


2. Given that the expected duration for a project path was 36 days and further suppose that someone calculated the standard deviation for the project path to be 2.4 days. What is the probability that the project takesnu A. Fewer than 40 days? S B. Longer than 30 days? C. Between 34 and 40 days