Question: 2 . If your earliest start is 8 and your latest start is 1 0 for the same activity in a CPM ( Critical Path

2. If your earliest start is 8 and your latest start is 10 for the same activity in a CPM (Critical Path Method) analysis, which of the following statement holds?
A. The earliest finish time must be 8 B. The slack for this activity is 2
C. The latest finish time must be 12 D. All of the above
E. None of the above
3. Flow time (not the theoretical flow time) can be defined as:
I. The time that a unit is being processed by the machines and workers in the system
II. The time that a unit which leaves the process has spent within the process
III. The time for a unit to move through the system

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!