Question: 2 . If your earliest start is 8 and your latest start is 1 0 for the same activity in a CPM ( Critical Path
If your earliest start is and your latest start is for the same activity in a CPM Critical Path Method analysis, which of the following statement holds?
A The earliest finish time must be B The slack for this activity is
C The latest finish time must be D All of the above
E None of the above
Flow time not the theoretical flow time can be defined as:
I. The time that a unit is being processed by the machines and workers in the system
II The time that a unit which leaves the process has spent within the process
III. The time for a unit to move through the system
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
