Question: - 2 igure 4 Consider the project crashing information presented in the figure above. What is the total cost of the project if you adopt

-2igure 4
Consider the project crashing information presented in the figure above. What is the total cost of the project if you adopt the least costly strategy to complete the project in 8 days?
$165
$170
$175
$195