Question: Activity Normal Time Normal Cost Crash Time Crash Cost Crash Cost Per Day A 3 40 2 80 40 B 2 20 1 80 60
| Activity | Normal Time | Normal Cost | Crash Time | Crash Cost | Crash Cost Per Day |
| A | 3 | 40 | 2 | 80 | 40 |
| B | 2 | 20 | 1 | 80 | 60 |
| C | 2 | 20 | 2 | 20 | N/A |
| D | 4 | 30 | 1 | 120 | 30 |
| E | 3 | 10 | 1 | 80 | 35 |
| F | 1 | 25 | 1 | 25 | N/A |
Figure 8-4 Project Crashing Information Consider the project crashing information presented in Figure 8-4. What is the cost to complete this project in the normal time?
| |||
| |||
| |||
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts