Question: Activity Normal Time Normal Cost Crash Time Crash Cost Crash Cost Per Day A 3 40 2 80 40 B 2 20 1 80 60

Activity Normal Time Normal Cost Crash Time Crash Cost Crash Cost Per Day
A 3 40 2 80 40
B 2 20 1 80 60
C 2 20 2 20 N/A
D 4 30 1 120 30
E 3 10 1 80 35
F 1 25 1 25 N/A

Figure 8-4 Project Crashing Information Consider the project crashing information presented in Figure 8-4. What is the cost to complete this project in the normal time?

a. $40
b. $405
c. $120
d. $145