Question: 2. Immediate Predecessors Activity Name A B D E F G Activity Duration 5 2 3 4 1 7 9 A B A, B D

2. Immediate Predecessors Activity Name A B D E F
2. Immediate Predecessors Activity Name A B D E F G Activity Duration 5 2 3 4 1 7 9 A B A, B D EG a) Draw an AON network diagram and include the critical path analysis. Remember the start circle. (10 marks) b) What is the total time required? (5 marks) c) What is the critical path? (5 marks) 2. Immediate Predecessors Activity Name A B D E F G Activity Duration 5 2 3 4 1 7 9 A B A, B D EG a) Draw an AON network diagram and include the critical path analysis. Remember the start circle. (10 marks) b) What is the total time required? (5 marks) c) What is the critical path