Question: (Critical Path Method) 1- Consider the table represented below: Activity Name A B D E F G Predecessor Duration time (weeks) 2 4 B 3

(Critical Path Method) 1- Consider the table

(Critical Path Method) 1- Consider the table represented below: Activity Name A B D E F G Predecessor Duration time (weeks) 2 4 B 3 AB 5 C,D 4 E 6 F 5 GF 4 I a) What is the project competition time? b) Show ES/EF and LS/LF for each node of the network. c) What is the critical path? d) If activity C increases by 1 week, does this change impact on the project competition time? Why