Question: 2 . Johnson Cogs wants to set up a line to produce 6 0 units per hour. The work elements and their precedence relationships are
Johnson Cogs wants to set up a line to produce units per hour. The work elements and their precedence relationships are shown in the following table.
Work Element TIME
sec Immediate
predecessor
A None
B A
C A
D B
E B
F C
G C
H D E
I F G
J H I