Question: 2 . Johnson Cogs wants to set up a line to produce 6 0 units per hour. The work elements and their precedence relationships are

2. Johnson Cogs wants to set up a line to produce 60 units per hour. The work elements and their precedence relationships are shown in the following table.
Work Element TIME
(sec) Immediate
predecessor
A 40 None
B 30 A
C 50 A
D 40 B
E 6 B
F 25 C
G 15 C
H 20 D, E
I 18 F, G
J 30 H, I