Question: 2. Management decided to implement the project described in the following table: (50%) Optimistic Time Most Likely Time Pessimistic Time Activity Predecessor(s) (weeks) (weeks) (weeks)
2. Management decided to implement the project described in the following table: (50%)
Optimistic Time Most Likely Time Pessimistic Time
Activity Predecessor(s) (weeks) (weeks) (weeks)
- 3 4 5
- 1 3 5
- A 3 3 5
- A,B 2 6 9
- C 2 4 5
- B,D 2 4 6
- C,E 2 3 4
- E,F 3 4 6
- G 2 3 5
- Draw the project network. (5%)
- What is the expected completion time of the project? (10%) (i.e., must list all the possible paths and find the longest one as the expected completion path)
- If one path has the longest expected completion time, why is it not necessarily the critical path? (5%)
- What are the variances for each activity?(10%)
- Assuming that the path completion times are independent, what is the probability of completing the project in 19 weeks? (10%)
- Given the same assumption as in part (e), what is the probability of completing the project in 16 weeks? (10%)