Question: 2. Match each project activity with its estimated variance time. Activity Optimistic Time Most Likely Time Pessimistic Time g 2 3 6 h 4 6
2. Match each project activity with its estimated variance time.
| Activity | Optimistic Time | Most Likely Time | Pessimistic Time |
| g | 2 | 3 | 6 |
| h | 4 | 6 | 8 |
| i | 3 | 4 | 6 |
Question 2 options:
|
The formula for the variance time of an activity is (b-a/6)^2 |
|