Question: 2. Match each project activity with its estimated variance time. Activity Optimistic Time Most Likely Time Pessimistic Time g 2 3 6 h 4 6

2. Match each project activity with its estimated variance time.

Activity

Optimistic Time

Most Likely Time

Pessimistic Time

g

2

3

6

h

4

6

8

i

3

4

6

Question 2 options:

f

d

e

The formula for the variance time of an activity is (b-a/6)^2

1.

.44

2.

.25

Step by Step Solution