Question: 2. Part 2: ( See figure 2 part 2 below ). Assume that Systems Analysis actually finished (duration) at 6 weeks, Design Input & Output
2.
Part 2: (See figure 2 part 2 below). Assume that Systems Analysis actually finished (duration) at 6 weeks, Design Input & Output actually finished (duration) at 3 weeks, and Design Database actually finished (duration) at 4 weeks. Can the project be completed in the required completion time of 30 weeks? Why or why not?

Part 2: Table for Part 2
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!