Question: 2 part. (I) A project is estimated to complete in 6 months. Refer to the table below. The total budgeted cost is $ till completion

2 part.
2 part. (I) A project is estimated to complete in 6 months.
Refer to the table below. The total budgeted cost is $ till

(I) A project is estimated to complete in 6 months. Refer to the table below. The total budgeted cost is $ till completion of the whole project. The cumulative budgeted cost is at the end of month 4 . (II) Below is a table of actual costs. The cumulative actual cost is $ at the end of month 4 . Is there a cost overrun? (note: please fill in Yes or No). (III) Below is a table of the cumulative percentages of work completed by the end of month 4 . The cumulative earned value of the project is : at the end of month 4. (Amounts are cumulatrve percent complete) (IV) At the end of month 4, CPI, (Note: keep two decimals) and CV- (V) If the project team guarantees that starting from month 5 they will finish 40% of Task 2 and 30% of Taks 3 each month, the whole project will be fully completed by the end of month

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!