Question: (I) A project is estimated to complete in 6 months. Refer to the table below. The total budgeted cost is $ till completion of the


(I) A project is estimated to complete in 6 months. Refer to the table below. The total budgeted cost is $ till completion of the whole project. The cumulative budgeted cost is $ at the end of month 4 . (II) Below is a table of actual costs. The cumulative actual cost is \$ at the end of month 4 . Is there a cost overrun? (note: please fill in Yes or No). (III) Below is a table of the cumulative percentages of work completed by the end of month 4 . The cumulative earned value of the project is $ at the end of month 4 . (Amounts are cumulative percent complete) (IV) At the end of month 4, CPI= , (Note: keep two decimals) and CV =
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
