points eBookHintPrintReferencesCheck my workCheck My Work button is now enabledItem Problem Static The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME WEEKS A B A C A D C E B D F D G E F b What is the critical path? multiple choice ACDFG ACDEG ABEG c How many weeks will it take to complete the project? d How much slack does activity B have?