2 points eBookHintPrintReferencesCheck my workCheck My Work button is now enabled1Item 2 Problem 4-7(Static) The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 6 B A 3 C A 7 D C 2 E B, D 4 F D 3 G E, F 7 b. What is the critical path? multiple choice A-C-D-F-G A-C-D-E-G A-B-E-G c. How many weeks will it take to complete the project? d. How much slack does activity B have?