Question: 2 Problem 5-14 (Static) 3 nts eBook Hint Print ferences Here is a CPM network with activity times in weeks: C(6) B(5) D(6) A(7)

2 Problem 5-14 (Static) 3 nts eBook Hint Print ferences Here is
a CPM network with activity times in weeks: C(6) B(5) D(6) A(7)

2 Problem 5-14 (Static) 3 nts eBook Hint Print ferences Here is a CPM network with activity times in weeks: C(6) B(5) D(6) A(7) (G(3) (F(8)) E(4) a. Determine the critical path. OA-E-F-D OA-E-G-C-D OA-B-C-D b. How many weeks will the project take to complete? Number of weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To solve this CPM Critical Path ... View full answer