Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 42-week completion date requested by the owner. The Mueller project manager prepared the following project network.
A project network with 10 activities and 14 directed arcs is shown.
Activity Start is connected to activity A.
Activity A is connected to activity B, to activity C, and to activity D.
Activity B is connected to activity F.
Activity C is connected to activity E and to activity F.
Activity D is connected to activity E.
Activity E is connected to activity G and to activity Finish.
Activity F is connected to activity G and to activity H.
Activity G is connected to activity H.
Activity H is connected to activity Finish.
Activity Finish has no arcs directed to other activities.
Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows.
| Activity | Optimistic | Most Probable | Pessimistic |
|---|---|---|---|
| A | 4 | 8 | 12 |
| B | 6 | 7 | 8 |
| C | 6 | 12 | 18 |
| D | 3 | 5 | 7 |
| E | 6 | 9 | 18 |
| F | 5 | 8 | 17 |
| G | 10 | 15 | 20 |
| H | 5 | 6 | 13 |
Help with b through e please
(a) Find the critical path. (Enter your answers as a comma-separated list.) (b) What is the expected project completion time (in weeks)? weeks (e) What should the construction company tell the owner? (Enter your free-form answer using as many characters as necessary.) This answer has not been graded yet
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts