Question: 2 pts A simple CPM network has five activities, A , B , C , D , and E . A is an immediate predecessor
pts
A simple CPM network has five activities, A B C D and E A is an immediate predecessor of and of B is also an immediate predecessor of and of and are both immediate predecessors of Which of the following statements is true?
There are paths in this network.
There are two paths in this network.
There are four paths in this network.
There are five paths in this network.
There are six paths in this network.