Question: Q1: A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B
Q1: A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor
of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate
predecessors of E. Draw the network path for this project.
Q2: A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B
and of C. B is an immediate predecessor of C. The activity durations are A = 4, B = 3, C = 8.What is the duration of the critical path.
Q3: Draw the critical path for the network activities shown below.
What is the duration of the critical path.
________.
Activity Duration Immediate Predecessors
A 4 --
B 2 A
C 7 --
D 4 A
E 5 B,C,D