Question: 2 pts begin{tabular}{|c|c|c|c|c|} hline Activity & Normal Time & Normal Cost & Crash Time & Crash Cost hline A & 3 & 40 &

2 pts \begin{tabular}{|c|c|c|c|c|} \hline
2 pts \begin{tabular}{|c|c|c|c|c|} \hline
2 pts \begin{tabular}{|c|c|c|c|c|} \hline Activity & Normal Time & Normal Cost & Crash Time & Crash Cost \\ \hline A & 3 & 40 & 2 & 80 \\ \hline B & 2 & 20 & 1 & 80 \\ \hline C & 2 & 20 & 2 & 20 \\ \hline \end{tabular} According to the Project Cash information above, which activity should you crash to reduce this project by one day with the least incremental cost? Activity A Activity C Activity E Activity F