Question: The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule.

The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project

three

weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs.

The table below contains information about an

Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.)

The table below contains information about an

The cost of shortening the project is $ _______

\begin{tabular}{ccccc} \hline Activity & Normal Time (weeks) & Crash Time (weeks) & Cost to Crash (\$ per week) & Immediate Predecessor(s) \\ \hline A & 5 & 4 & 250 & None \\ B & 10 & 9 & 200 & None \\ C & 8 & 7 & 270 & A \\ D & 7 & 4 & 350 & A \\ E & 3 & 3 & & B \\ F & 1 & 1 & & C, D \\ G & 5 & 3 & 250 & D, E \\ H & 8 & 7 & 450 & F \\ I & 1 & 1 & & G \\ \hline \end{tabular} \begin{tabular}{cc|cc} \hline Activity & Time according to schedule (weeks) & Activity & Time according to schedule (weeks) \\ \hline A & & F & \\ B & & G & \\ C & & H & \\ D & & & \\ E & & & \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!