Question: 2 Question 24 (1 point) A Project Manager is conducting cost risk planning and is calculating Earned Monetary Value for a high-risk work activity estimated
2 Question 24 (1 point) A Project Manager is conducting cost risk planning and is calculating Earned Monetary Value for a high-risk work activity estimated at $20,000. The risk probability is 25%. The risk estimated residual value is $ 4000. The Project Sponsor is assigning a total Management reserve of $8000 for the project. What is the total amount the Project Manager should assign as the cost estimate? 45 $36,000 48 $ 24,000 $ 29,000 $ 25,000
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
