Question: Question 30 (1 point) A Project Manager is conducting cost risk planning and is calculating Earned Monetary Value for a high-risk work activity estimated at

Question 30 (1 point) A Project Manager is
Question 30 (1 point) A Project Manager is conducting cost risk planning and is calculating Earned Monetary Value for a high-risk work activity estimated at $20,000. The risk probability is 25%. The risk estimated residual value is $ 4000 The Project Sponsor is assigning a total Management reserve of $8000 for the project. What is the total amount the Project Manager should assign as the cost estimate? $ 29,000 $ 25,000 $ 36,000 $ 24,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!