Question: 2. (Short answer question, 20.0 points) Process Arrival Burst Time P108 P2 32 P313 P4 5 4 1) Draw the scheduling charts for preemptive short

2. (Short answer question, 20.0 points) Process Arrival Burst Time P108 P2 32 P313 P4 5 4 1) Draw the scheduling charts for preemptive short job first (SJF) and non-preemptive SJF. 2) Compute the average waiting time for the two cases