Question: 2. (SHOW YOUR COMPLETE WORK) A project network is shown below, with three time estimates (Optimistic Time-Most Likely Time-Pessimistic Time (in weeks)) for each activity

 2. (SHOW YOUR COMPLETE WORK) A project network is shown below,

2. (SHOW YOUR COMPLETE WORK) A project network is shown below, with three time estimates (Optimistic Time-Most Likely Time-Pessimistic Time (in weeks)) for each activity in the network. a. Compute the expected time for each activity in the project network. [8 points] b. Identify and list all possible paths in the project network. Compute the expected duration for each path in the project network. [13 points] c. Identify the critical path(s) in the project network. What is the expected project completion time? d. Compute the variance of each activity on the critical path(s). [3 points] e. Determine the project variance and project standard deviation. [3 points] [4 points] Use the PERT analysis results in 2(c) and 2(e) above to answer questions (f), (g), (h), and (i) below: f. What is the probability that the project can be completed within 36 weeks of its start? [3 points] g. What is the probability that the project can be completed within 27 weeks of its start? [4 points] h. Determine the project deadline that gives this project a 73% chance of on-time completion. [5 points] i. Determine the project deadline that gives this project a 13% chance of on-time completion. [6 points]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!