Question: 2 . The 4 0 - year design discharge is used in a drainage system. It is expected that after 1 5 years, the drainage

2. The 40-year design discharge is used in a drainage system. It is expected that after 15 years, the drainage system will be replaced by a new drainage structure (service life \(=\)15 years)
a) What is the probability that the design discharge will be exceeded on the first 2 years after construction?
b) What is the probability that the design discharge will be exceeded two times over the period of 15 years?
c) Compute the risk and reliability of the project throughout its service life.
d) If the return period is 50 years, what is the probability that the design discharge will not be exceeded exactly on 5th and 10th year for a period of 15 years?
2 . The 4 0 - year design discharge is used in a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!