Question: 2. The following table shows activities on a critical path for a project with corresponding optimistic, most likely, and pessimistic times in days. Complete the

2. The following table shows activities on a

2. The following table shows activities on a critical path for a project with corresponding optimistic, most likely, and pessimistic times in days. Complete the table calculations and answer the following questions. Activity To Tm Te A 40 50 96 100 110 F 92 100 120 G 20 30 34 H 40 46 58 66 Use PERT analysis to find the expected duration of this critical path. Use PERT analysis to find the variance and standard deviation of this critical path. Find the probability that project can be completed in less than 340 days