Question: 2) The table below shows the activities in a project and their pessimistic, most likely and optimistic durations and the expected time for each activity.

2) The table below shows the activities in a

2) The table below shows the activities in a project and their pessimistic, most likely and optimistic durations and the expected time for each activity. E Activity A B D E F m 3 6 6 a 2 5 5 3 2 3 9 b 4 7 7 5 4 5 16 X 6 6 4 3 4 4 3 4 11 Y a) Work out the values of X and Y. (2 marks) b) The project has the following critical paths. DO NOT DRAW THE NETWORK DIAGRAMS. A-C-D-F C-D-E-F A-B-D-F Determine the completion time that the project manager should quote with a 90% certainty