Question: The table below shows the activities in a project and their pessimistic, most likely and optimistic durations and the expected time for each activity. Activity
The table below shows the activities in a project and their pessimistic, most likely and optimistic durations and the expected time for each activity.
| Activity | a | m | b | Et |
| A | 2 | 3 | 4 | X |
| B | 5 | 6 | 7 | 6 |
| C | 5 | 6 | 7 | 6 |
| D | 3 | 4 | 5 | 4 |
| E | 2 | 3 | 4 | 3 |
| F | 3 | 4 | 5 | 4 |
| G | 9 | 11 | 16 | Y |
- Work out the values of X and Y.
- The project has the following critical paths. DO NOT DRAW THE NETWORK DIAGRAMS.
A-C-D-F
C-D-E-F
A-B-D-F
Determine the completion time that the project manager should quote with a 90% certainty.