Question: 2 Upvotes guaranteed. Please answer completely Q4 The network diagram of a project is shown below. (a) Use two-pass method to determine the critical path.

2 Upvotes guaranteed. Please answer completely
2 Upvotes guaranteed. Please answer completely Q4 The network diagram of a
project is shown below. (a) Use two-pass method to determine the critical

Q4 The network diagram of a project is shown below. (a) Use two-pass method to determine the critical path. (3 points) (b) What is the project duration? ( 1 points) (c) What is the slack time of activity F? (1 points) (d) Activities A, B, C, D can be crashed. The normal time, crash time, normal cost and crash cost are shown in the table below. What is the daily crash cost of each activity? ( 2 points) (e) The project needs to be completed in 22 days. How can you achieve this goal at minimum cost? Please report your crashing steps in the table below. (The table size does not imply number of steps.) ( 3 points)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!