Question: 2 . Use Johnson's rule to determine the optimal sequencing for the five jobs to be processed on two machines in a fixed order (

2. Use Johnson's rule to determine the optimal sequencing for the five jobs to be processed on two machines in a fixed order (Machine 1 before Machine 2). The processing times are given in the table below.
(a) What is the optimal sequence?
(b) What is the total flow time for this sequence?
Job Machine 1 Machine 2
L
M
N
0
p
16
11
18
7
14
9
6
7
10
15