Question: Use Johnson's rule to determine the optimal sequencing for the five jobs to be processed on two machines in a fixed order (Machine 1 before
- Use Johnson's rule to determine the optimal sequencing for the five jobs to be processed on two machines in a fixed order (Machine 1 before Machine 2). The processing times are given in the table below.
|
Job | Machine 1 | Machine 2 |
| L | 8 | 7 |
| M | 9 | 6 |
| N | 8 | 9 |
| O | 3 | 4 |
| P | 7 | 5 |
- What is the optimal sequence?
- What is the total flow time for this sequence?
- Please determine which job(s) being processed in time 15?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock