Question: 2. Use the information to create a Gantt chart for the project. (10 marks) 3 B5 1 Survey Designed 4 2 6 5 E7 Develop

2. Use the information to create a Gantt chart

2. Use the information to create a Gantt chart for the project. (10 marks) 3 B5 1 Survey Designed 4 2 6 5 E7 Develop 8 presentation 13 2 15 13 F 15 0 A 3 0 Contract Signed 033 6 D 13 0 Data Collection 67 [13] o Analyze Results 13 2 15 15 H 16 0 Presentation 15 1 16 3 C6 o Target 336 6 G 8 7 Demo- graphics 13 2 15 Market ID Legend ES ID EF SL Description LSDUR LF