Question: 2. Using the data below, create the project schedule using normal times. Determine the order in which you would crash the project one day, two

2. Using the data below, create the project schedule using normal times. Determine the order in which you would crash the project one day, two days, and so on until it is in an all-crash mode. Identify how much it would cost for each day you crash the schedule Activity B D E F G Predecessor A B B, C D. F. F Normal Time 12 6 Normal Cost- 300 400 150 -100 Crash Time U 4 Crash Cost 350 300 450 600 225 650 Crash Cost per Day