Question: 2. Using the image below, Activity A has planned duration of 10 days and budget $15,000. What is the update for day 4 (Data Date)?

 2. Using the image below, Activity A has planned duration of

2. Using the image below, Activity A has planned duration of 10 days and budget $15,000. What is the update for day 4 (Data Date)? Work Performed= 35% Actual cost of work performed= $3,400 a. Is the activity ahead/behind schedule? (Express it in $ value) b. Is the activity over/under budget? 0 A 10

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!