Question: 2. Using the image below, Activity A has planned duration of 10 days and budget $15,000. What is the update for day 4 (Data Date)?

2. Using the image below, Activity A has planned duration of 10 days and budget $15,000. What is the update for day 4 (Data Date)? Work Performed= 35% Actual cost of work performed= $3,400 a. Is the activity ahead/behind schedule? (Express it in $ value) b. Is the activity over/under budget? 0 A 10