Question: 2. Using the network above and the additional in- formation below, find; (a) The crash cost per day (b) Which activities should be crashed to

2. Using the network above and the additional in-
2. Using the network above and the additional in-
2. Using the network above and the additional in- formation below, find; (a) The crash cost per day (b) Which activities should be crashed to meet a project deadline of 13 days at minimum cost. Assume partial crashing. Crash Time Crashed Cost (total) Normal Time (days) Normal Cost Activity A 3 B $500 325 550 250 1 4 4 3 4 3 7 5 $300 250 400 150 D