Question: 2 . Using your completed chart above, calculate the following: a . Avg Job Lateness 2 6 days late, and a total of 5 jobs,
Using your completed chart above, calculate the following:
a Avg Job Lateness
days late, and a total of jobs, so we would divided days by The avg. job lateness is days
b Makespan
Markspan is the total time to process all jobs which would days
c Flow Time
Flow time is the sum of times each job spends waiting, and being processed.
d Average Flow Time
e Average # Jobs in System
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
