Question: 2 . Using your completed chart above, calculate the following: a . Avg Job Lateness 2 6 days late, and a total of 5 jobs,

2. Using your completed chart above, calculate the following:
a. Avg Job Lateness
26 days late, and a total of 5 jobs, so we would divided 26 days by 5=5.2. The avg. job lateness is 5.2 days
b. Makespan
Markspan is the total time to process all jobs which would =20 days
c. Flow Time
Flow time is the sum of times each job spends waiting, and being processed.
d. Average Flow Time
e. Average # Jobs in System