Question: 2 - What is the late start time for Activity E given the activity times and precedence requirements shown in the table? table [

2- What is the late start time for Activity E given the activity times and precedence requirements shown in the table?
\table[[Activity,Time,Predecessor],[A,4,-],[B,7,-],[C,8,A],[D,2,A],[E,4,B],[F,5,C, D],[G,9,E, F],[H,7,G]]
a)14
b)13
c)12
d)15
Bo brak
 2- What is the late start time for Activity E given