Question: What is the late start time for Activity E given the activity times and precedence requirements shown in the table? Activity Time Predecessor A 5

What is the late start time for Activity E given the activity times and precedence requirements shown in the table?

Activity

Time

Predecessor

A

5

--

B

7

--

C

8

A

D

7

A

E

4

B

F

8

C, D

G

9

E, F

H

7

G