Question: 2. What will be the probability that the project will be completed in 20 weeks & 18.5 weeks? 0 mi The activities (for constructing municipal

 2. What will be the probability that the project will be
2. What will be the probability that the project will be completed in 20 weeks & 18.5 weeks?

0 mi The activities (for constructing municipal buildings), their immediate predecessors, & time requirements are given in following Table: Activity Time Required (wecks) Column Column2 Immediate Normal Column3 Crash Column4 P Predecessors Weeks Ssss Weeks SSSS 4 5 4 4000 2 1000 2 3 4 3 3600 2 4800 3 4 5 4 3200 3 5000 7 8 9 18 9600 14 8400 4 4 5 1 14 1600 3 2000 1 2 4 3 2 1200 1 2500 4 5 6 4 5 3000 3 4000 8 1 2 4 7 2 1600 1 2400 9 3 4 4 S 4 14400 2 6000 10 1 1 2 2 2 1600 1 2000 18 20 26 20 7200 16 8400 12 1 2 3 8 2 1600 1 2400 13 1 1 2 6. 9, 10, 11 1 1000 10.5 1800 14 0.1 0.14 0.16 13 0.14 600 10.14 600 IS 0.2 0.3 0.4 14 0.3 700 0.3 700 16 1 1 2 1 800 0.5 1200 17 1 2 3 16 2 1600 1 2000 18 3 5 7 15, 17 5 4400 3 6000 19 0.1 0.9 0.2 16 1 1400 2200 20 0.14 0.16 19 0.14 500 10.14 500 21 2 6 19 3 3000 2 4000 22 20 0.1 400 10.1 400 23 0 0.2 21,22 0.2 300 0.2 300 Requirements: 1. Determine the Total Project Completion Time, Critical Path and Slack time for all activities involved 2. What will be the probability that the project will be completed in 20 weeks & 18.5 weeks? 3. Determine the least cost of reducing the project completion date by 3.5 weeks 10,5 0.1 0.1 0.1 0.2 0.2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!