Question: 2. When is the Earliest (in weeks) that Task H can finish (EF)? 3. When is the latest (in weeks) that Task G can start?

2. When is the Earliest (in weeks) that Task H can finish (EF)? 3. When is the latest (in weeks) that Task G can start? 4. What is the latest (in weeks) that Task D can start?
5. Which of the following tasks has the most slack?
a) Task A b) Task B c) Task C d) Task D e) Task E
6. How long will the project take to complete (weeks)? 7. The critical path for this project is:
1) A-B-D-G-I
2) A-C-F-F-I
3) A-B-D-F-H-I
4) A-B-E-G-I
8. If the time that it takes to complete Task G can be reduced from 16 weeks to 12 weeks, that is Earliest Finish for G is reduced to 12 weeks, how many weeks sooner can the project be completed?
Consider a project made up of the following tasks: Predecessors Weeks Task A 2 B A 4 A 5 B 3 EU OU I - B 4 F 2 C D D, E G 6 H F 4. | G H 6 Draw the project network (don't need to upload). Complete the forward and backward pass to answer the following questions. Q. When is the earliest (in weeks) that Task B can finishStep by Step Solution