Question: 2. Which Control Chart is most useful when plotting the proportion of defective invoices in a Monitoring Plan? An X & MR or I &
2.
Which Control Chart is most useful when plotting the proportion of defective invoices in a Monitoring Plan?
An X & MR or I & MR Chart
A Run Chart
A P Chart
A Histogram
3.
Given the improved process, if the volume goes above 300, then the manager has to bring cross-trained staff in from production. Which of the following would best characterize this plan?
The Data Collection Plan
The Implementation Plan
The Pilot Plan
The Response Plan
3.
Which of the following would be a good reason to document the project?
To ensure the process is not changed in the future
To be able to replicate the improvement
To ensure the team gets paid