Question: 20. In developing work breakdown structure (WBS), starting at the top level with the largest items of the project and systematically developing increasing levels of

20. In developing work breakdown structure (WBS), starting at the top level with the largest items of the project and systematically developing increasing levels of detail for all work activities, is what kind of approach?

Group of answer choices

a. Top-down approach

b. Analogy approach

c. Bottom-up approach

d. Mind-mapping approach