Question: 20 min left QUESTION 19 Crashing is a method in project management that helps you speed up the timeline of a project through the addition

20 min left

20 min left QUESTION 19 Crashing is a method in project management

QUESTION 19 Crashing is a method in project management that helps you speed up the timeline of a project through the addition of resources O True O False QUESTION 20 Which of the following best describes Float? O A. Ensures your project doesn't sink O B. Is the duration of delay allowed within non-critical activities (tasks) so as to not impact the critical path. O C. Float and Slack are the same thing O D. All of the above