Question: 2.2 A project has just completed the 87th item in its plan. It was scheduled to have spent $168,000 at this point in the plan,

2.2 A project has just completed the 87th item in2.2 A project has just completed the 87th item in

2.2 A project has just completed the 87th item in its plan. It was scheduled to have spent $168,000 at this point in the plan, but has actually spent only $156,000. The foreman estimates that the value of the work actually finished is about $162,000. What are the spending and schedule variances for the project? What are the SPI and CPI? What will be the trend of the project? (Over or Under budget? & Ahead or Behind Schedule?) Please make sure 100% before sending the answer. Thank you

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!