23 Activity A B OA) 0 B) 4 O 98 O D) 10 OE) None of the above TEODRY C F Immediate Predecessor A B C,D B Time 432745 The following represents a project with known activity times. All times are in weeks. Using the data in Table, what is the latest possible time that C may be started without delaying completion of the project? (2 Points)