Question: 23 Activity Immediate Predecessors Normal Cost ($) Crash Cost ($) Normal Time (weeks) 8 3 7 3 3 Crash Time (weeks) 6 2 A AB

23 Activity Immediate Predecessors Normal Cost

23 Activity Immediate Predecessors Normal Cost ($) Crash Cost ($) Normal Time (weeks) 8 3 7 3 3 Crash Time (weeks) 6 2 A AB D EE 5 1 2 D E F G 4000 2000 2000 3000 1000 2000 1500 6000 2500 3000 3500 1500 3500 2500 6 2 4 1 Given the information in the table, What will be the second activity/ies that must be considered to crash the time of the project to 17 weeks? In (2 Points) O E , C D O B,C