Question: Question 2: Software Installation Project Activity Immediate Predecessor Normal Cost Crash Cost Crash Time (Weeks) Max reduction $ per Week Normal Time (weeks) 5 A

Question 2: Software Installation Project

Question 2: Software Installation Project Activity Immediate Predecessor Normal Cost Crash Cost Crash Time (Weeks) Max reduction $ per Week Normal Time (weeks) 5 A 3 B 8 7 A 10 8 D 4 3 E A, B B D 3 $2,000 $5,000 $10,000 $3,000 $4,000 $8,000 $2,000 $6,000 $7,000 $4,000 $8,000 $12,000 $7,000 $5,000 $14,000 $2,000 $9,000 $15,000 2 6 F 9 G 2 H E, F G C, F 8 2 5 7 I 9 Penalty: $1000/ week beyond 25 weeks Indirect Project Costs: $ 2500 Per Week

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!