Question: 2.3 Throughput (TH) = Work In Process (WIP) x Cycle Time (CT) Throughput time = 5 days x 7 hours = 35 hours Need to
2.3 Throughput (TH) = Work In Process (WIP) x Cycle Time (CT) Throughput time = 5 days x 7 hours = 35 hours Need to mark 500 exam scripts in 5 days (working 7 hours a day). Takes 1 hour to mark a script. How many markers are needed? [5 Marks]