Question: 24/25 Determining the latest finish time (LF) and latest start time (LS) for each activity is known as the through the network O A forward
24/25
Determining the latest finish time (LF) and latest start time (LS) for each activity is known as the through the network O A forward pass B. slacking OC. backward pass OD. crashing Mr. Flux requested that a number of non-standard items be incorporated into the design of his client's car audio system. One method for formally handing these adjustments is by OA supply chain design QB modular architecture OC concurrent engineering OD engineering change