Question: 25. In PERT, the critical path is the path through the project network. A. optimal B. minimal C. shortest D. longest 26. Given the following

 25. In PERT, the critical path is the path through the

25. In PERT, the critical path is the path through the project network. A. optimal B. minimal C. shortest D. longest 26. Given the following information for a project, find the earliest start time (in days) of activity C, supposing the project starts at day 0. Activity Immediate Activity Predecessor Time (days) A (start) 6 B (start) C A.B D B 4 F C.D 3 A. 5 B. 6 C. 8 D. 14